2024/2025 Approved Variation Order Policy

[featured_image]
  • Version
  • Download 716
  • File Size 234.35 KB
  • File Count 1
  • Create Date June 1, 2024
  • Last Updated November 14, 2024

2024/2025 Approved Variation Order Policy

Both construction projects and services contracts may vary from the original design, scope and definition. Whether small or large, projects may inevitably depart from the original tender design, specifications and drawings prepared by the design team.

This can be because of technological advancement, statutory changes or enforcement, change in conditions, geological anomalies, non-availability of specified materials, or simply because of the continued development of the design after the contract has been awarded.